FDP Mold Remediation
Trade name of 365svc
877-402-7788
Estimate #834140 | September 24, 2026

Mold Remediation

Detailed estimate & proposed scope of work

Customer / Project Location
Mount Sinai Baptist Church
1646 3rd Street Northwest
Washington, DC 20001
Estimate Reference
#834140
Original date: September 24, 2026
Equipment allowance: 3 days
Itemized Cost Breakdown
# Work Item Quantity Rate Amount
01 Containment and negative pressure 4 areas $199.00 per area $796.00
02 HEPA air scrubbers, 500 CFM 4 units x 3 days $200.00 per unit/day $2,400.00
03 LGR dehumidifiers 4 units x 3 days $175.00 per unit/day $2,100.00
04 Drywall removal - basement bathroom 1 allowance $930.00 $930.00
05 Drywall removal - second-floor closet 1 allowance $380.00 $380.00
06 Drywall removal - room 304 closet 1 allowance $715.00 $715.00
07 Antimicrobial fogging 1 service $495.00 $495.00
08 HEPA negative-pressure duct cleaning / third-floor vent treatment 1 service $2,000.00 $2,000.00
09 Remediation debris disposal 1 service $550.00 $550.00
10 Final work-area cleaning 1 hour $310.00 per hour $310.00
Total Estimated Project Cost $10,676.00

Tax: Not applicable, as listed in the original estimate. Equipment unit rates are calculated from the original grouped daily charges: $800/day for four scrubbers and $700/day for four dehumidifiers.

Location confirmation required. Four containment areas are priced, but only three are named: the basement bathroom, the second-floor closet and the room 304 closet. The fourth area remains to be identified.

Pricing and listed quantities are retained from the original estimate. Expanded work descriptions on the following pages are proposed clarifications for confirmation before final issue.

FDP Mold Remediation
Trade name of 365svc
877-402-7788
Estimate #834140 | September 24, 2026

Detailed Scope of Work

Containment, equipment, treatment and closeout details

A. Site Controls & Equipment $5,296.00
01 Containment and negative pressure $796.00
4 contained areas x $199.00 per area

Establish temporary barriers and controlled access for four designated work areas during removal and cleaning. Configure the listed HEPA equipment for the proposed negative-pressure arrangement. Named areas: basement bathroom, second-floor closet and room 304 closet. Confirm the fourth location.

Containment barrier setup
Basement bathroom entry
Second floor closet
Second-floor closet barrier
Room 304 closet
Room 304 containment
02 HEPA air scrubbers - 500 CFM $2,400.00
4 units x 3 days x $200.00 per unit/day = 12 equipment-days

Provide four 500-CFM HEPA air scrubbers, one in each contained area, for the three-day allowance. Coordinate placement and exhaust configuration with the containment arrangement, and operate the units during the scheduled remediation period. The combined equipment rate is $800.00 per day.

03 LGR dehumidification $2,100.00
4 units x 3 days x $175.00 per unit/day = 12 equipment-days

Provide four low-grain refrigerant (LGR) dehumidifiers, one in each contained area, for humidity reduction during the three-day allowance. The combined equipment rate is $700.00 per day. This is the priced duration, not a documented drying result or guaranteed completion time.

B. Selective Drywall Removal $2,025.00
04 Basement bathroom - drywall removal $930.00
1 lump-sum removal allowance

Remove the affected drywall in the basement bathroom within the agreed boundaries. Confirm removal limits before cutting, work within containment, and collect debris for the separately listed disposal service. Demolition square footage and cut height are not specified.

Affected wall section
North wall moisture damage
Lower baseboard area
Cut line boundary
05 Second-floor closet - drywall removal $380.00
1 lump-sum removal allowance

Remove the affected drywall within the second-floor closet. Limit demolition to the agreed affected sections, protect adjoining surfaces during the work, and collect removed material for disposal. The allowance is lump sum; no square footage is specified.

06 Room 304 closet - drywall removal $715.00
1 lump-sum removal allowance

Remove the designated drywall within the closet in room 304. Coordinate removal with containment and debris handling. Square footage and cut height are not specified. Insulation removal, framing removal and replacement finishes are not separately itemized in the original estimate.

C. Antimicrobial Treatment & HVAC $2,495.00
07 Antimicrobial fogging $495.00
1 treatment service

Provide the antimicrobial fogging service listed in the original estimate. Before application, confirm the product, authorized application method, treatment locations and applicable occupancy or re-entry instructions. Coverage area and application volume are not specified. No clearance testing or whole-building treatment scope is defined by this line item.

08 Duct cleaning and third-floor vent treatment $2,000.00
1 HEPA negative-pressure cleaning service

Perform the listed air-duct cleaning using HEPA-filtered negative pressure and brushing, with sanitizing, disinfecting and antimicrobial treatment of the third-floor vents. Confirm the connected duct system, access points, vent count and treatment product. Additional floors, additional HVAC systems, and separate coil or blower services are not identified.

D. Debris Disposal & Final Cleaning $860.00
09 Remediation debris disposal $550.00
1 disposal service

Collect, contain and remove the debris generated by the listed drywall-removal activities, and arrange the associated disposal. Coordinate movement of debris with the contained work areas. No dumpster size, debris weight, special-waste classification or number of hauling trips is specified in the source estimate.

10 Final work-area cleaning $310.00
1 hour x $310.00 per hour, as listed in the original estimate

Perform final cleaning of the designated work areas after the listed remediation activities, including collection of remaining work debris and cleanup of accessible work-area surfaces. Retain the original one-hour allowance. Laboratory testing and independent post-remediation verification are not part of this listed cleaning charge.

Scope Confirmations Before Final Issue